How tall will Dominion Energy build the emission stacks?
Dominion Energy plans to build a compressor station directly across the Potomac River from Mount Vernon. While they claim the emission stacks will only be 50 feet tall Dominion Energy has submitted very conflicting data to the Maryland Department of Energy and the Federal Energy Regulatory Commission.
Stack Heights from Dominion Energy's Permits
November 2016
Air Permit to Construct Application Dominion Cove Point LNG, LP, Charles Compressor Station, Eastern Market Access Project Dominion to MDE, 9 November 2016
Section 4.2.3 Good Engineering Practice Stack Height, Page 4-5 (PDF page 27)
The maximum calculated GEP stack height for the new emissions sources is 83 feet; the controlling structure is the proposed compressor building (33 feet).
Section 4.4.1 Emission Rates and Exhaust Parameters, Pages 4-5 through 4-9 (PDF pages 27-31)
November 2016
Maryland Department of Energy Application for Fuel Burning Equipment, 7 NOVEMBER 2016
Page 2
Read the entire documentExhaust Stack Information 50 feet
November 2016
Federal Energy Regulatory Commission Documents, Abbreviated Application for a Certificate of Public Convenience and Necessity 15 NOVEMBER 2016
3-4 through 3-5 (PDF page 1033-1034)
Read the entire documentThe maximum calculated GEP stack height for the new emissions sources is 83 feet; the controlling structure is the proposed compressor building (33 feet).
November 2016
Dominion Cove Point LNG, LP, Eastern Market Access Project, Docket No. CP17-_______-000
Resource Report 9, Air and Noise Quality
NOVEMBER 2016
Page 3-5 (PDF page 175)
Read the entire documentThe maximum calculated GEP stack height for the new emission sources is 83 feet; the controlling structure is the proposed compressor building (33 feet).
January 2018
Federal Energy Regulatory Commission Order Issuing Certificate 23 JANUARY 2018
Page 50
114. Theresa Lazar states that air will be trapped near her home due to a 100-foot-high hill to the east of the Charles Station. But the station site is not surrounded by hills that would trap air within a low valley. Also, the compressor units at the Charles Station will discharge exhaust at a minimum speed of 15.84 meters per second from stacks reaching 83 feet above ground level.200
Citation 200: Application, Res. Report 9, app. 9-C at 3-5 (stack height), 3-8 tbl.3-2 (Stack Parameters and Emission Rates).
Read the entire documentMarch 2018
Supplement A to Docket #24-16 Dominion Energy Cove Point LNG, LP – Charles Station Dominion to MDE, 09 March 2018
This packet includes: Dominion Cove Point LNG, LP, Charles Compressor Station, Eastern Market Access Project Revision 2 – FEBRUARY 2018
Tables 4-2 and 4-3 (pictured above) show the stack height at 15.24 meters or 50 feet.
Section 4.2.3 Good Engineering Practice Stack Height, Page 4-5 (PDF page 63)
Read the entire documentThe maximum calculated GEP stack height for the new emissions sources is 113.5 feet; the controlling structure is the proposed compressor building (45.4 feet).
March 2018
Supplement B to Docket #24-16 Dominion Energy Cove Point LNG, LP – Charles Station Dominion to MDE, 15 March 2018
This packet includes: Dominion Cove Point LNG, LP, Charles Compressor Station, Eastern Market Access Project Revision 1 – APRIL 2017
Dominion Cove Point LNG, LP, Charles Compressor Station, Eastern Market Access Project Revision 2 – FEBRUARY 2018
Tables 4-2 and 4-3 (pictured above) show the stack height to be 15.24 meters or 50 feet.
Section 4.2.3 Good Engineering Practice Stack Height, Page 4-5 (PDF page 63)
The maximum calculated GEP stack height for the new emissions sources is 113.5 feet; the controlling structure is the proposed compressor building (45.4 feet).
Read the entire document